? Many vested elements tried to subvert the project by instigating the innocent people against
         NPCIL over transfer of land for the project.

    ? Notification in 2009 issued under the Old Act ended up in court litigations, counter claims and
         objections coupled with outbursts of public agitations

    ? New Act (RFCTLARR Act 2013) came into force w.e.f 01-01-2014 and it mandated equal
         compensation to assignees at par with private land owners. Even the occupiers on government
         land were entitled to compensation

Challenges Faced

It was a major challenge which the District Administration to convince the Project affected families that
the intended social and environmental impacts would outweigh the benefits from the project; regaining
trust and faith on the machinery towards fair compensation by ushering in transparency and
accountability in LA and R&R.

To make inroads in to the villages by cutting down the middlemen, technological interventions and
effective implementation of the provisions of the progressive LARR Act were the only options
available. Stake holder consultations were done at every instance of LARR.

    ? Major breakthrough happened in the form of Social Impact Assessment (SIA), Economical
         Impact Assessment (EIA), Gram Sabhas, Social Economical Survey (SES) and field studies.

    ? A Project Level Committee (PLC) drawing participants from the community, Women, SC/ST,
         Youth, elected public representatives, etc. under the chairmanship of Minister and District
         Collector with the Joint Collector, Project Administrator LARR as the convener

    ? Comprehensive Information & Communication Technology (ICT) tools were not developed
         across the country to help the LA and R&R in such massive projects.

    ? There were no capacities in staff to handle the technical studies like Social Impact Assessment
         (SIA), Environmental Impact Assessment (EIA) and ICT tools viz computers, cell phones, video
         conference for arriving at compensation.

    ? Components like SIA, Land Alienation, Land acquisition, Compensation for trees and structures
         on the project affected area, R&R package computation, R&R colony allotments etc. needed to
         be computerized to disallow the discretion and delays.